Garage Conversion ADU in Miami Gardens: What It Runs and What’s Realistic
A garage conversion ADU in Miami Gardens typically runs $35,400 – $94,400 for the conversion itself, and a full turnkey job with kitchen, bath and separate utility metering lands in the $53,100 – $153,400 range. Most conversions take 3 to 5 months from permit to final inspection. Call (844) 797-4868 for a free on-site estimate and a written, line-item scope before any work begins.
How a Garage Conversion ADU Comes Together, Stage by Stage

What follows is the real sequence for a garage conversion in this market, with the decisions you’ll make and roughly how long each phase eats up. The build starts before day one: on the estimate walkthrough we photograph the slab, check whether the existing garage floor is level enough to float a finish over, measure ceiling height (8 feet is the floor for livable space here), and confirm where the electrical panel sits relative to the conversion.
Stage 1: Permits and design (4 – 8 weeks). This is the longest wait and the one that trips up homeowners who expect a quick start. A garage conversion is a change of use, so you’ll file with Miami-Dade County for a building permit covering the conversion, the electrical, plumbing and mechanical scopes, plus wind-load detailing. During this stretch you decide the layout: where the kitchenette lives, whether the bathroom is a half or a full, and whether you want a separate entrance. If the ADU will be rented for more than 30 days at a time, mention that up front so we document the living area and egress correctly.
Stage 2: Demo and slab prep (3 – 5 days). The existing garage door comes off, any carport tie-in or block wall that isn’t staying gets removed, and the slab gets ground and leveled. This is where we find out whether the floor needs a self-leveling pour. In most of the homes we work in, it does, since garage slabs were poured for trucks, not tile. A Sakrete patch-and-level product handles the shallow spots; deeper dips get a full topping.
Stage 3: Rough-in (2 – 3 weeks). Framing for interior partitions, electrical, plumbing and HVAC happen here, and this is where the two big cost variables show up. If the garage slab is post-tension, cutting for a new drain line is off the table without engineering, and we may route the bathroom plumbing overhead instead. If the electrical panel is a legacy 100-amp unit already carrying window AC and a dryer, it may need to be upgraded. Both of these are things you’ll see priced as line items before work starts, not surprises mid-build.
Stage 4: Insulation, drywall and finishes (3 – 5 weeks). Spray foam or batt insulation, drywall, tape and texture, flooring, trim and paint. You’ll pick flooring here, and the choice matters more in Miami Gardens than in a lot of places because humidity and slab moisture will punish the wrong pick.
Stage 5: Inspections and final (1 – 3 weeks depending on county scheduling). Rough-in inspections, then final. We schedule inspections and pull permits as part of the scope, and you receive the passed inspection record at closeout. Final walkthrough is where the punch list gets written, and the work sits behind the 730-Day Done Right Promise afterward.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Actually Make on a Garage Conversion ADU
- Flooring underfoot. Porcelain tile is the default for a reason: it handles slab moisture, wipes clean, and runs $6 – $14/sq ft installed. Luxury vinyl plank looks warmer and installs in a day, but in a converted garage it needs a vapor barrier or it will cup. Polished concrete is the cheapest per square foot and looks industrial; it’s not for everyone, but it’s durable and easy to cool.
- Ceiling and AC. A ductless mini-split is how most of these ADUs get cooled, since tying into the house system often overloads it. Mini-splits run $3,500 – $7,000 installed for one or two zones. If the main house HVAC is oversized enough, a ducted tie-in is possible but more permitting.
- Kitchenette vs. full kitchen. A kitchenette with a sink, undercounter fridge, microwave and two-burner cooktop uses less space and drops the plumbing scope. A full kitchen with a range and dishwasher adds utility load and venting. Most Miami Gardens conversions land in the middle: sink, cooktop, no dishwasher.
- Bathroom. Half bath (toilet and sink) is the cheapest at roughly $5,900 – $14,160; a full bath with shower moves into the $10,600 – $33,000 range depending on tile and fixture grade. Tub-to-shower conversion is a common pick because it fits tighter footprints.
- Windows and exterior door. If the garage opening gets framed in for a wall, you’re adding windows and an entry door. In this market they need product approval for the High-Velocity Hurricane Zone, so expect impact-rated openings rather than standard. That adds cost, but the wall behind them doesn’t need retrofitting later.
- Water heating. Tankless is compact and frees closet space; a 40-gallon tank is cheaper to buy and install. Both work, tankless costs more upfront.
What Garage Conversion ADU Costs in Miami Gardens, FL

Plan on $35,400 – $94,400 for the conversion of an existing garage. A separate kitchen, bath and utility line pushes into the larger range. The lead range for these jobs is $53,100 – $153,400 once you’re building a turnkey rental or family suite.
| Item | Typical Range |
|---|---|
| Core conversion (framing, insulation, drywall, flooring, paint) | $35,400 – $65,000 |
| Bathroom addition | $10,620 – $33,040 |
| Half bath | $5,900 – $14,160 |
| Kitchenette | $10,620 – $23,600 |
| Mini-split HVAC | $3,500 – $7,000 |
| Electrical panel upgrade if needed | $3,000 – $6,500 |
| Impact windows and entry door | $5,310 – $17,700 |
What moves the number up or down: (1) existing garage condition, especially whether the slab needs leveling and whether the walls are block or wood-frame; (2) whether plumbing has to be run overhead because of a post-tension slab; (3) whether the electrical panel can carry a new AC and kitchen load; (4) material grade, which is where the biggest swing lives, since tile at $6/sq ft and porcelain at $14/sq ft look the same in a bid sheet; (5) whether you want separate metering, which is a utility and permitting scope of its own. A written line-item estimate from us lists each of these as the number you see is the number you pay. What’s typically excluded: furniture, appliances beyond what we specify in the line items, and any structural repair revealed after demo.
See the difference
Before
After
Before
After
Before
AfterWhat Miami Gardens Homes Specifically Do to This Job
Miami Gardens is a built-out postwar suburb, and most of its housing went up from the late 1950s through the 1980s. That means the garages we convert here are mostly original: single-story concrete block with stucco, low-pitch or flat roof tie-ins, carports converted at some point or still open, and slabs poured well before anyone thought about an ADU. Near Hard Rock Stadium and along the Palmetto and Opa-locka industrial edges, we see a lot of block-and-stucco homes where the stucco over masonry has aged and any alteration pulls in a fair bit of detailing. The county’s High-Velocity Hurricane Zone rules govern the openings and fasteners we use, so a framed-in garage door wall needs product approval for its windows and door, not a stock window from a big-box shelf.
The flat and low-slope roofs common in the older subdivisions mean ponding and aging roof-ceiling assemblies are a real thing to plan around. A mini-split needs proper flashing at the wall penetration, and any tie-in roof work has to detail the transition correctly or you’re buying mold. We schedule exterior work around afternoon storms, which is why the roof and wall phases get slammed early in a build cycle. If the wider project involves more than the garage, we’d point you to our Home Additions & ADU in Miami Gardens page for the broader scope. We cover conversions throughout Miami Gardens, including Opa-locka, Golden Glades and Westview adjacent properties. If the driveway and garage apron are in rough shape from the old car traffic, homeowners often pair this with Concrete Driveways & Concrete Work in Miami Gardens to clean up the approach, or with Asphalt Driveways & Resurfacing in Miami Gardens on the older homes that still have asphalt aprons.
Serving Miami Gardens, FL – Our Local Coverage Area
We serve Miami Gardens and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: Garage Conversion ADU in Miami Gardens

The build itself takes 3 to 5 months once permits are in hand, and permitting adds another 4 to 8 weeks. County review of a change-of-use permit is where most of the waiting happens. Total timeline from signing to final inspection is commonly around 5 to 7 months. Call (844) 797-4868 for a schedule estimate on your specific garage.
Yes, a garage conversion requires a building permit through Miami-Dade County. It’s a change of use, and because the county is in the High-Velocity Hurricane Zone, the structural changes and openings have to meet wind-load and product-approval requirements. We pull the permit and schedule the inspections as part of the job. Call (844) 797-4868 to talk through your scope.
Sometimes. If the existing garage sits away from the house’s plumbing stack and the slab is post-tension, we may be able to route drains through the wall or overhead and skip the structural work. If the bathroom location needs a cut into post-tension, that’s engineering territory. This is something we check on the estimate walkthrough, not after demo.
Conversions run $35,400 – $94,400, with turnkey jobs including kitchen, bath and separate utilities landing in the $53,100 – $153,400 band. The variables are slab condition, plumbing routing, electrical capacity, material grade and metering. Call (844) 797-4868 for an exact quote; estimates are free and itemized.
Every garage conversion we build carries the 730-Day Done Right Promise, and if it’s not done right we make it right. That covers workmanship on framing, drywall, electrical, plumbing and finish work. Manufacturer warranties on windows, HVAC and appliances run separately. Call (844) 797-4868 to review the details before you sign.
Schedule Your Free Garage Conversion Estimate
We’ll walk your garage, measure the slab and ceiling, check the panel and plumbing stack, and hand you a written line-item estimate for a garage conversion ADU in Miami Gardens with no change orders hiding in it. Calls are answered by a live person around the clock at (844) 797-4868. The estimate and design consult are free, and we’ll tell you straight if the garage isn’t a good candidate. Our Home Additions & ADU team handles the permit work and the inspections.