New Detached ADU in Miami Gardens, FL: What the Project Actually Takes
A new detached ADU in Miami Gardens typically runs $53,100 to $153,400 and takes 6 to 10 months from first survey to the final inspection on the certificate of occupancy. Most of that time is permitting and site work, not framing. The county reviews every structure here against High-Velocity Hurricane Zone rules, so the wind-rating paperwork often shapes the schedule as much as the weather does. Call (844) 797-4868 and we’ll walk your lot and give you a written, line-item number before you commit to anything.
The Sequence We Follow for a New Detached ADU

Every detached unit we build moves through the same five stages. Here’s what happens, roughly when, and what you’ll be deciding along the way.
Stage 1: Site survey and geometry (week 1 to 2). We measure setbacks, check the location of your septic or sewer lateral, and look at drainage. An auxiliary dwelling footprint won’t pass review if it sits on the setback line or blocks the swale, and Miami Gardens lots can be tight. You’ll decide placement and whether the unit faces the house or the street.
Stage 2: Permit drawings and approval (month 1 to 3 or 4). This is the long pole. Structural plans, wind-load calculations, product approvals for impact-rated openings, and mechanical, electrical and plumbing drawings all go in together. Miami-Dade County review can take several rounds. You’ll sign off on the design before submission and pick your exterior finish and roof style so the drawings match what gets built.
Stage 3: Site preparation and slab (weeks 1 to 4 of construction). Clearing, grading, and pouring the slab on grade with the anchor hardware set for a wind-rated structure. This is also where we run the underground plumbing stubs so the slab doesn’t get cut later. The concrete crew and the plumber coordinate closely, and homeowners often pair this with Concrete Driveways & Concrete Work in Miami Gardens to finish the access path while the equipment is already on site.
Stage 4: Framing, envelope, and roof (weeks 4 to 10). Walls go up, the roof structure goes on, and the envelope gets closed and dried in before interior work starts. Impact-rated windows and doors get installed at the stage the inspection schedule requires. You’ll confirm interior trim and paint colors around week 6.
Stage 5: Interior finish and final inspection (weeks 10 to 16). Cabinets, flooring, fixtures, final electrical, and the punch list. The county signs off, you get a certificate of occupancy, and the unit is livable. Total build time on a straightforward detached ADU is typically 4 to 5 months once the permit clears.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Pick Between for a Detached Unit
Detached units here come in a few tested configurations. The choice usually comes down to how you’ll use it and how much upkeep you want to take on.
- Site-built vs. panelized: A stick-built ADU gives you total flexibility on layout and matches the main house. A panelized kit (Abodu and Dvele are two of the better-regarded systems) arrives faster and can shave weeks off construction, but the panels still have to meet Miami-Dade wind-load and product-approval rules, and you’re locked into their module sizes.
- Impact-rated openings: Non-negotiable in this county. Impact glass runs more than standard units but removes the shutters, the storage, and the scramble before every storm. Worth it every time.
- Roof type: Standing-seam metal holds up best to wind and rain and costs more up front. A shingle roof with the correct underlayment and fasteners is less expensive and passes, provided the wind-rating documentation is in order. Low-slope and flat designs are common on the main houses here but add waterproofing detail on a new structure.
- Slab and utilities: A slab-on-grade unit is standard. Running plumbing out to a detached footprint is the biggest hidden variable, so decide early whether you’re tying into the main sewer lateral or working with a separate connection. Sakrete concrete mix and similar products come up in finish work, but the structural slab is poured on site.
- Exterior finish: Stucco over block matches the neighborhood’s look and takes paint well. Fiber cement panels (James Hardie) are a durable, low-maintenance alternative if you want a different profile. Both hold up here if the detailing is right.
What a New Detached ADU Costs in Miami Gardens, FL

The full range for this project is $53,100 to $153,400. That spread is wide because the variables below move the number more than the size of the unit does. The lower end is a compact, efficient, slab-on-grade unit with simple finishes and no plumbing surprises. The upper end is a larger, fully finished unit with premium systems, upgraded appliances, and a complicated site.
What pushes the number up or down:
- Size and layout: A studio up to a two-bedroom unit. Every additional bedroom adds plumbing, electrical, and square footage.
- Utility runs: Trenching, running water and sewer out to the detached footprint, and upgrading the panel can add real money. If the main house panel is already maxed, a subpanel or service upgrade is part of the bid.
- Site access and grading: A tight lot, a fence to pull, or a tree that has to come down. Grading and drainage work here is not optional given summer rain.
- Material grade: Flooring, cabinetry, fixtures, and appliances are where you control the spend. A modest kitchenette looks the same in photos as a full kitchen and costs a fraction.
- Permit scope: Impact openings, wind-load engineering, and the structural review are all required and all priced into the bid, not billed separately.
A written estimate covers the slab, framing, envelope, roof, impact openings, MEP rough-in and trim, interior finishes, and permit and inspection fees. It doesn’t cover landscaping, a detached driveway or patio you add later, or furnishing the unit. Everything is covered by our 730-Day Done Right Promise, and upfront pricing means the number you see is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhat Miami Gardens Homes Do to a New Detached ADU Project
Most of this city was built out between the late 1950s and the 1980s, which means almost every lot already has a house, a carport, and established drainage that a new structure has to work around. Near Hard Rock Stadium and along the Palmetto, we’re often working behind low-pitch or flat roofs and aging stucco over concrete block, and the setbacks are tight. The county’s High-Velocity Hurricane Zone rules apply to the new unit, so every opening is impact-rated, the roof fasteners and underlayment carry product approval, and the structural plans show wind-load calculations. The subtropics mean the same thing here as anywhere in Miami-Dade: a slab that has to be graded to shed water, waterproofing details on every horizontal surface, and exterior work scheduled around afternoon storms. If your finishes are going in during hurricane season, we protect them and hold the schedule.
Serving Miami Gardens, FL – Our Local Coverage Area
We serve Miami Gardens and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: New Detached ADU in Miami Gardens

Expect 6 to 10 months total, with the build itself taking 4 to 5 months once the permit is issued. Permit review is the biggest variable and it’s out of our hands, so we submit complete drawings the first time to avoid a second round.
Yes. Every detached ADU requires a building permit and final inspection through Miami-Dade County, and the structure has to meet wind-load and product-approval requirements. We pull the permits and manage the inspections as part of the job.
Often yes, but it depends on your existing panel and lateral capacity. If the main panel has room, a subpanel and a dedicated run usually cover it. If it’s already loaded, we’ll recommend an upgrade and price it in the written estimate so there are no surprises.
No. We price from a written scope and the number you sign is the number you pay, unless you ask for a change. The 730-Day Done Right Promise covers workmanship for well beyond the first two years.
All work is covered by our 730-Day Done Right Promise, and factory warranties on impact windows, roofing materials, and appliances pass through to you. That’s our written commitment, not a verbal one.
Get a Free Estimate for Your New Detached ADU in Miami Gardens
Call (844) 797-4868 for a free on-site estimate. We’ll walk your lot, review what your property can support, and give you a written, line-item quote with the full scope and a realistic schedule. A live person answers around the clock, and a background-checked technician arrives in uniform. If your project includes broader changes to the main house, see our Home Additions & ADU service and our full Miami Gardens page. You can also pair a new unit with Paver Driveways in Miami Gardens to finish the entry approach. For the whole scope of work, our Home Additions & ADU in Miami Gardens page shows everything we handle under one roof.
From foundation to finish line, built to last, backed in writing. Ask about $1,000 off projects over $10,000 and 0% financing for 18 months.
Written by the team at Groundwork Construction Co.